The AsstrA Project Logistics (AIPL) team has successfully concluded a large-scale transportation project, delivering 1,936 freight tons of oversized cargo from Korea to Poland for Técnicas Reunidas-Hyundai Engineering Poland Joint Venture. The job was done within the scope of Orlen Oil Refinery Upgrade Project. The project, which began in January, has now been completed with the final delivery to the Orlen refinery in Płock, Poland.
Key highlights of the project include:
- Cargo Volume: 1,936 freight tons of oversized cargo
- Origin: Korea
- Destination: Płock, Poland (Orlen refinery)
- Transit Route: Sea transport to Gdańsk, followed by land transport to Płock
- Project Duration: January to March 2025
- Cargo Units: 25, including oversized crates
The shipment commenced on January 4 under a part-cargo arrangement aboard an AAL vessel, adhering to FOB shipping terms. AsstrA's tailored logistics approach ensured the safe and efficient transit of this complex cargo.
Maksim Platonov, Business Development Manager at AsstrA, stated: "Our team's customized logistics approach met the unique demands of this oversized and complex cargo transportation. We're pleased to report that all cargo has been successfully delivered without any incidents, damage, or unexpected costs".
The successful completion of this project underscores AsstrA's expertise in handling challenging logistics operations. The company's ability to manage such complex deliveries from start to finish, including the final leg from Gdańsk to Płock, demonstrates their comprehensive project management capabilities.
This achievement marks another milestone for AsstrA in the field of project logistics, reinforcing their position as a reliable partner for global clients with complex transportation needs.